Christmas Island Power Station

EDL

Project Delivery

Construct

Deliver

Design

Situation

Our client required an upgrade to the existing power generation facility to support increased demand for industrial and domestic use. Located in a remote, offshore environment, the logistics challenges were presented.

Solution

Aerison were engaged as the primary contractor to deliver engineering and design, fabrication and installation works for the following scope items:

  • The acoustically treated and fire rated generator halls to house four (4) Wartsila W6L32 gensets allowing for future removal/installation of any of the gensets.
  • Ventilation systems and engine exhaust systems including roof mounted mufflers.
  • Structural, mechanical, piping, electrical and instrumentation works.

Particular Features:

  • The enclosure was designed to provide a four-hour fire rating for all wall partitions

Project Highlights:

  • Complete building, equipment and components were engineered and designed to be suitable for containerised transport.
  • Complete project was delivered from Australia for assembly on Christmas Island.
  • Equipment and components designed to withstand the harsh coastal environment conditions of Christmas Island.
  • Individual generator halls supplied with filtered ventilation air and the electrical control room temperature-controlled air conditioning.
  • Generator enclosure designed to meet strict noise requirements of 85 dB(A) sound pressure at 1m.

Outcome

  • Design and construction activities were delivered safely with no reportable incidents.
  • Reduced onsite construction activity through pre-assembly and modular build methods. Despite inclement weather conditions, the project was completed ahead of schedule within the allocated cost.